To complete each record in the process of ball mill commissioning

View previous topic View next topic Go down

To complete each record in the process of ball mill commissioning

Post by paulzhao on Mon Jan 13, 2014 1:38 pm

Mill commissioning of cooling and lubrication system should work properly. Main bearings, transmission bearing , reducer temperature should be normal . Mill commissioning work should seriously do the recording . Mill installation is complete , after passing inspection , commissioning can be empty .
Ball mill commissioning by skilled operatives responsible for , and strictly comply with safety procedures ball .
1 , empty mill operation no less than 12-24 hours of continuous operation , operation found the problem should be solved . Mill air operation can be carried out properly load test machine commissioning . Load test run should be carried out in stages . Load operation should be conducted , as the nesting feeding, avoid unnecessary ball and cylinder liner wear loss and damage.
2 , add the appropriate material and 1/ 3 the number of balls ( the maximum amount of ball mill See description ) commissioning 12-24 hours.
3 , was added to 2 /3 of the number of balls run 24-48 hours.
According mill discharge , the qualified product yield , similar reference to the actual amount of ball mill concentrator to determine the reasonable amount of this station ball mill , be not less than 72 hours of commissioning.
Increase above the amount and duration of load commissioning time to running- gear case size and gear reducer ( temperature , noise, tooth contact , etc. ) as a basis for determining . Before contact with the tooth surface accuracy does not meet the design requirements, may not operate at full capacity .
http://www.vipeakballmill.com/ball.asp

paulzhao
Guest


Back to top Go down

View previous topic View next topic Back to top

- Similar topics

 
Permissions in this forum:
You cannot reply to topics in this forum